Bearings BetaFunding & opportunities · North West UKGet email alerts

Guides › Public contracts

Writing the bid: method statements, evidence and the scoring behind the marks

How evaluators score public tenders, what moves a 3 to a 5, the price formula, and a method for writing answers that earn the marks, with templates.

SMEsFoundersCharities and social enterprises20 min readChecked 18 October 2026
On this page
  1. The reality
  2. How evaluators work, in their own rules
  3. The scoring ladder, and what moves a 3 to a 5
    1. Price: the formula and the arithmetic
  4. The method, from pack to portal
    1. 1. Read the pack: a compliance matrix and a response plan
    2. 2. Plan each answer: the question's bullets are your subheadings
    3. 3. Write it: answer first, then numbers and the "so what" test
    4. 4. Evidence: one case study, many answers
    5. 5. Risks and KPIs: the part that earns the 4
    6. 6. Price: set the strategy from the split
    7. 7. Clarification questions: early, anonymous, logged
    8. 8. Review and submit: a critical friend, a consistency check, 24 hours out
  5. Real answers, weak and strong
  6. After the result
  7. Pitfalls
  8. Checklist: before you press submit
  9. Questions
    1. How are UK public sector tenders scored?
    2. What is the difference between a 3 and a 5 in a tender evaluation?
    3. How is price scored in a tender?
    4. What is a method statement and how should I structure it?
    5. Can evaluators take into account what they already know about my company?
    6. What feedback do I get if I lose a public tender?
    7. How long does it take to write a tender?
  10. Sources

A tender is scored by two or three people with a descriptor ladder, a word limit and not much time. Here are their rules in their own words, how price becomes points, a real North West evaluation, and templates for answers that score. See also Finding tenders, How public procurement works now and Social value.

  • Evaluators score only what is on the page, independently, then moderate. "Prior knowledge/experience/assumptions etc. cannot be taken into consideration" (Cheshire East, March 2025).
  • On Liverpool City Council's 2026 ladder "minor weaknesses or lacks clarity" is a 3; a 5 adds "some areas of the service above the level of requirements".
  • Price is usually lowest bid ÷ your bid × price weight. In Liverpool's 2026 evaluation the cheapest bidder finished third.
  • Mirror the question: its bullets are your subheadings, your first sentence is the answer.
  • Compliance kills before quality is read: late, over the word limit, a missing pricing schedule, an unsigned form.
  • Under the Procurement Act you receive the winner's scores and reasons. Log every loss.

The reality

  • Up to 10 days to build a good bid, "sometimes more" for complex contracts (GOV.UK)26
  • 60/40 and 70/30 the commonest quality/price splits, a bid platform's estimate; no public dataset confirms it24
  • 3rd where the cheapest of five bidders finished, Liverpool City Council, 13 October 202613
  • 9.24 of 10 the social value gap between that winner and the cheapest bidder13
  • 0 on any question an automatic fail at Liverpool, "grounds for excluding" at Brent1316
  • 24 hours before the deadline: the last full portal and document check (a bid consultancy's rule)21

How evaluators work, in their own rules

Buyers' guidance and Liverpool's 2026 report describe the same process113810:

How a tender is evaluated
  1. Compliancelate, incomplete or over-length bids can be set aside
  2. Independent scoringeach panel member scores the quality answers alone
  3. Price, separatelyno evaluator assesses both quality and price
  4. Moderationa documented meeting agrees the final scores
  5. Clarificationonly what is "ambiguous, inconsistent or unusual"
  6. Assessment summaryyour scores and the winner's, with reasons
  7. Standstillat least eight working days before signature

The rules behind it, in buyers' words:

Rule Who says so So you
Panel members "read and score the quality/technical aspects of the tenders independently"; a moderation meeting agrees final scores by a process "fully transparent and documented" Procurement Journey1. Liverpool consolidated each evaluator's sheet into a "master evaluation workbook" before moderation13 Write for the least expert, most hurried person on the panel
Read "at face value" and "score on the basis of the information provided"; do not "read between the lines" Procurement Journey1 Nothing is implied. Every requirement gets a sentence that answers it
"Contracting Authorities are only permitted to take into consideration information provided within your response. Prior knowledge/experience/assumptions etc. cannot be taken into consideration." Cheshire East, March 202515 Incumbents lose here most. Put the track record on the page
"anything over the limit may be disregarded"; under the Act a tender "over the prescribed word count" may be disregarded entirely Cheshire East15; GOV.UK7 Count every answer
"If your submission is late, it cannot be accepted"; the portal "will not allow you to submit after the deadline has passed" Cheshire East15; Westmorland and Furness31 Internal deadline a day early
"A full justification of scoring is especially important where a bid has failed to meet the 'acceptable' expectation" Procurement Journey1 Give them a quotable sentence per requirement, evidence beside it
The assessment summary must explain each score by reference to "relevant information in the tender", and "where useful" why a higher score was not awarded GOV.UK assessment summaries guidance, paragraphs 22 to 268 Your feedback should name the requirements you missed. Ask if it does not
"no member of the evaluation panel should assess both the quality/technical elements and the commercial elements" Procurement Journey1 The quality reader cannot see your price. Value claims must stand alone
Clarification after submission covers only what is "ambiguous, inconsistent or unusual"; "Negotiations in relation to price or other areas where improvements may be possible should not take place" Supplier Journey3; Liverpool's clarifications were "specific to their bid"13 Nothing can be added later
"Poor quality submissions give a bad impression of the quality of the goods/services your Organisation provides, and this may be reflected in the scoring" Cheshire East15 Formatting is scored, indirectly

Cheshire East to its bidders: evaluators "won't have huge amounts of time to review lengthy responses", and a response should not "require the evaluator to search through reams of documentation to find an answer". "Any alterations to forms/templates provided may also invalidate your response." No unrequested attachments, and do not "refer the evaluator to generic marketing information"15.

The scoring ladder, and what moves a 3 to a 5

Two real ladders: a North West council in 2026, and a London borough in 2017 under the old Public Contracts Regulations 2015 (pre-Act, but typical of descriptor scales).

Score Liverpool City Council, 2026 (quoted essentials)13 Brent Council, 2017, PCR era (quoted essentials)16
5 "Addresses all of the requirements and provides a highly detailed, robust and unambiguous response with relevant supporting evidence where no weaknesses are identified ... with some areas of the service above the level of requirements, which includes innovation and/or added value" "Strong evidence that all ... requirements can be met and the proposal exceeds expectation i.e. exemplary in the industry provides full confidence and no concerns"
4 "Addresses all of the requirements and provides a comprehensive response with relevant supporting evidence, where no weaknesses are identified, giving the Authority high confidence" "Good evidence that all the ... requirements can be met. Full and robust response, any concerns are addressed so that the proposal gives confidence"
3 "Addresses all of the requirements and provides a response with relevant supporting evidence but contains minor weaknesses or lacks clarity in some areas" "Some good evidence"; "satisfactory in most respects and there are no major concerns"
2 "Partially addresses the requirements ... contains weaknesses which lack explanatory detail or clarity" "Some minor omissions"; satisfies basic requirements "in some respects but is unsatisfactory in other respects"
1 "Fails to address most of the requirements or provides supporting evidence that is of insufficient detail" "Insufficient evidence"; "significant omissions, serious and/or many concerns"
0 Inadequate or no response Information "omitted or fundamentally fails to meet" requirements

Read it upwards, using Liverpool's own words13:

What each rung adds (Liverpool City Council, 2026)
  1. 45 Excellentplus "some areas of the service above the level of requirements"
  2. 34 Good"comprehensive", "no weaknesses are identified"
  3. 23 Satisfactoryall requirements, evidence, but "minor weaknesses or lacks clarity"
  4. 12 Partial"Partially addresses the requirements"

So remove every unevidenced claim and unclear sentence, then add one specific, costed extra. Length closes nothing. Scottish buyers use 0 to 4 or 0/25/50/75/100 with the same words at the top: "Comprehensive, unambiguous"2.

Knock-outs come before ranking. Brent (2017): "If a score of 0 is awarded to any one or more question or less than 3 in two or more questions, this will give grounds for excluding that ITT"16. Liverpool: "a minimum score of three for critical questions. A score of 0 for any question would be an automatic fail"13. Cheshire East: fail a pass/fail question and "your response will be rejected"15.

The 3-to-5 test, per answer

For each requirement: answered in its own sentence? A number, name or document beside the claim? Nothing a stranger could call unclear? One costed extra above the requirement? Four yeses fits the 5 descriptor; the first two alone fit a 3.

Price: the formula and the arithmetic

Most buyers score price relative to the lowest bid. Brent: "The best (lowest) price receives the maximum score ... remaining bids receive a score pro rata", that is (lowest bid ÷ your bid) × the price weight16. Liverpool: "the lowest price being offered the full available weighting"13.

With a price weight of 40, a £50,000 bid against a lowest bid of £40,000 scores 40 × 40,000 ÷ 50,000 = 32 points. A 4 out of 5 on a question weighted 23% earns 23 × 4 ÷ 5 = 18.4 points16. Pricing 10% above the cheapest costs 40 − 40 ÷ 1.1 = 3.6 points; 15% above costs 5.2. One extra mark on the 23% question is worth 4.6, so on a 60/40 split one mark on a heavy question buys back a 10% price gap.

The Act's guidance warns buyers about "the potential negative impacts on value for money of the use of relative scoring mechanisms", so expect variants such as price per quality point or bands; the method must be in the tender documents7.

Liverpool City Council's October 2026 evaluation weighted technical 60%, social value 10% and price 30%, and nine of its 28 technical categories carried all 60 technical marks13:

Liverpool City Council, 2026: the weightings
  • Technical 60%
  • Social value 10%
  • Price 30%
Where Liverpool's 60 technical marks sat (2026)
PCN lifecycle management26
System interfaces and integration13
Mobilisation and data migration7
Data security and backup4
Case management integration2.5
Support SLAs2.5
Disaster recovery2
Contract exit2
Account management1

Liverpool City Council, 13 October 2026: five bidders, and the cheapest came third

A further competition under ESPO's Parking Management Solutions framework for a penalty charge notice and permit system, estimated at £806,814.79 excluding VAT over up to seven years, closing 30 July 2026, run under the 2015 Regulations because the framework pre-dates the Act14. Social value used the National TOMs (Themes, Outcomes and Measures), scored "relative to the highest scoring bidder"; the lowest price took full marks13.

Bidder Technical (60) Social value (10) Price (30) Total, rank
D 56.80 10.00 24.76 91.56, 1st
E 55.00 5.89 20.66 81.55, 2nd
C 49.30 0.76 30.00 80.06, 3rd
B 46.60 0.60 23.54 70.74, 4th
A 51.90 1.50 6.25 59.65, 5th

D beat the cheapest bidder, C, by 11.50 points: +7.50 technical, +9.24 social value, −5.24 price. Social value, a tenth of the marks, was the biggest swing, because comparative scoring left three of the five bidders under 2 out of 10. On the usual formula D's 24.76 implies a price about 21% above the cheapest; price was split across two categories, so treat that as an estimate. The evaluator comment on the winner, in full: "They submitted a written offer which achieved scoring for the Technical criteria primarily ranked as good-excellent. They have submitted a social value proposal which provides good value to the local community." Its price "was within the affordability envelope for the project" and it "passed the financial checks conducted by PCS who conducted a check on Creditsafe"13.

Why it won: 56.8 of 60 means its weighted answers averaged above a 4, and one well-built TOMs schedule outweighed the cheapest bid's price advantage. All five bidders cleared the thresholds; the weighted questions and social value decided it.

The method, from pack to portal

Executive Compass, Thornton & Lowe and Stotles, quoted below, are commercial bid consultancies or platforms: their advice is practice, not buyer rules.

1. Read the pack: a compliance matrix and a response plan

Build two documents in the first hour: a compliance matrix of every instruction that can disqualify you, and a response plan of the scored questions with weightings, owners and review dates17. Non-compliance gives the buyer "an easy option to thin the pile", so return every document "in the format they were issued" and watch the clarification log, because deadlines change20.

COMPLIANCE MATRIX (one row per instruction, quoted from the pack)
Ref      | Instruction                                          | Where    | Owner | Done | Checked by
ITT 3.2  | "Responses must not exceed 1,000 words per question" | Q1 to Q8 | PW    | [ ]  |
ITT 4.1  | Form of Tender signed by a director, as PDF          | Doc 2    | JD    | [ ]  |
ITT 4.3  | Pricing Schedule in the Excel issued, no changes     | Doc 4    | AK    | [ ]  |
ITT 5.0  | Upload to The Chest by 12:00, 14 Nov 2026            | Portal   | PW    | [ ]  |
Clar. 7  | Revised specification of 2 Nov replaces section 6    | Q3, Q5   | JD    | [ ]  |

Conditions of participation (financial standing, insurance, technical ability) are gates, not scores. Under section 22 they must be proportionate, and insurance cannot be required before award, so a broker's quote is enough at bid12.

Then allocate words and hours by weighting (in Liverpool's tender two categories held 39 of 60 technical marks13), which "will give you an indication of the importance of the specific topic area to the award decision" (Cheshire East)15.

2. Plan each answer: the question's bullets are your subheadings

"The easiest way to lose points is to make your proposal difficult for the evaluator to score. Mirror the structure of the tender document exactly"24. Use the question's headings and keywords, in the order asked2325. "Remember, initially buyers have to scan bids" (GOV.UK)26. The skeleton is a synthesis of this guide's sources, not a buyer's template.

METHOD STATEMENT SKELETON (the question's own parts come first)
1. Direct answer (two sentences): the requirement in the buyer's words,
   your approach, the benefit to this contract.
2. Understanding: the buyer's context and outcomes, citing its own
   documents (specification clause, KPI, strategy, pipeline notice).
3. Method: numbered steps or phases. Each: who (named role), what,
   when, with what tools and standards. Sub-headings = the question's bullets.
4. Evidence: one STAR case study with numbers; accreditations; data.
5. Quality and KPIs: what you measure, how often, reported to whom,
   in the buyer's KPI names.
6. Risks: two or three specific to this contract, each with an owner
   and a mitigation.
7. Added value: one or two extras above the requirement, specific,
   costed, tied to a stated outcome. No unpriced promises.
Word check: inside the limit, words allocated to the weighting.

GOV.UK's SME guide builds a model answer as feature, method, value, evidence, advantage, and reminds bidders that "a tender is a sales document"27.

3. Write it: answer first, then numbers and the "so what" test

Would your opening paragraph score alone? "Do not make the evaluator search for your answer"22. Then:

Instead of Write Why it scores
"We are experienced" "98% on-time delivery ([n] jobs, [year]); 4.8/5 satisfaction ([n] responses)" Brent's 4 needs "good evidence", its 5 "strong evidence"2516
"We are innovative" The innovation and its measured effect, for example a 25% cut in response times "Evaluators score benefits"24
"Suitable and sufficient personnel" "Two operatives and a working supervisor per round, named in Appendix B, with a trained cover pool of four" "a specific number of personnel"23
"We aim to respond within 24 hours" "We will respond within four working hours (your KPI 3), logged in [system], reported monthly" Unequivocal, in the buyer's own KPI22
"Our award-winning team will work closely with the Council" Who does what, when, and what the Council sees as a result The "so what" test22

4. Evidence: one case study, many answers

Write case studies as Situation, Task, Action, Result (STAR)24. The Government Commercial Agency asks for "the most recent and relevant evidence and experience" with measurable outcomes28.

STAR CASE STUDY (120 to 180 words, one per answer)
Situation: [Client, place, year]. [The problem, with a number.]
Task:      [What we were contracted to do: scale, constraint, KPI.]
Action:    [What we did, step by step; who led it (role); tools;
            the decision that made the difference.]
Result:    [Outcome in numbers against the baseline; the client's
            KPI met or beaten; a dated reference contact or quote.]
Relevance: [One sentence: why this maps to this question's requirement.]

A practice tip rather than a sourced rule: one contract can serve mobilisation, quality, risk and social value answers. Write it long once, then cut 150 words per question, leading with the result that question scores.

5. Risks and KPIs: the part that earns the 4

The step from 3 to 4 is "any concerns are addressed" (Brent) and "no weaknesses are identified" (Liverpool)1613. Name the two or three risks the buyer worries about, with owners, triggers and reporting, and do not over-promise: Bracknell Forest Council wants a method statement "realistic and thorough, but does not contain promises as to levels of ... Services that cannot be achieved or maintained"30.

RISK TABLE ROW (two or three per answer, specific to this contract)
Risk:        [What could go wrong on this contract, in the buyer's terms]
Likelihood / impact: [L/M/H] / [L/M/H]
Trigger:     [The early sign you watch for, and who watches]
Mitigation:  [What you do before it happens, costed and resourced]
Response:    [What you do within x hours if it happens]
Owner:       [Named role]   Reported: [Where the buyer sees it, how often]

Where you have a gap, commit to closing it by a date. GOV.UK's example is committing to accreditation within six months27; Warwick's strong quality answer below does the same.

6. Price: set the strategy from the split

Thornton & Lowe's worked case is 40% price and 60% quality: "The full 40% score on pricing then going to cheapest or lowest priced bid submission", so everyone else must ask "Can you increase your quality tender scores to balance up your higher tender pricing?"18

Split What usually wins Your move
Price 50% or more, relative formula The lowest credible price Bid only if you can sit within a few percent of the cheapest. Run the calculator
60/40 or 70/30 quality to price Marks on the heavy questions Price fairly, then spend the time on the questions holding most of the marks
80% to 100% quality (Executive Compass has seen all three)21 Evidence and method Price is a gate, not the contest
Price per quality point, or bands Depends on the formula Model it first; the method must be in the documents7

A low price needs a visible logic: before disregarding a tender as abnormally low the buyer "must first notify the supplier and provide it with a reasonable opportunity to demonstrate that it will be able to perform the contract"7. "Check totals, check units, check assumptions, check that every deliverable is costed", and avoid "Unexplained efficiencies or 'economies of scale' claims"19. Cost the full delivery including overheads in the schedule provided4, with team sizes identical to the technical answers25.

7. Clarification questions: early, anonymous, logged

Cheshire East: "you are permitted to ask for clarification and the Contracting Authority is obliged to provide it but make sure you ask the question within the timescales". Answers "(not of a commercially sensitive nature) all have to be circulated to all other tenderers"15. So ask early174, reveal neither your identity nor your pricing position418, and read everyone else's questions.

CLARIFICATION QUESTION (one point per question, no identifying detail)
Document and clause: ITT section 6.3; Pricing Schedule, tab 2
Question: Row 14 applies a 12-month rate to a 36-month line. Please
confirm whether bidders should enter the annual or the whole-life
figure, and whether cell F14 will be corrected in a revised schedule.
Why it matters to all bidders: comparability of price scores.

8. Review and submit: a critical friend, a consistency check, 24 hours out

Run three reviews: compliance against the matrix, quality against the descriptors, and a "red team" read by someone new to the bid24; GOV.UK puts the outside read "two thirds of the way through the process"26. Finish with a check that figures match across sections and the pricing schedule17. Attach only what is requested, page-referenced from the answer30. Then a full portal and document review "no less than 24 hours before the deadline"21, an upload hours early with file sizes tested, and the receipt kept25.

Real answers, weak and strong

Real example: Warwick District Council's published pairs

Warwick District Council publishes paired weak and good answers, the only buyer-published pairs found. Both below are quoted from its supplier page29.

Weak: health and safety (Warwick District Council)

Question: "Do you have a Health & Safety Policy?" Answer: "Yes, see Appendix 1"

Strong: health and safety (Warwick District Council)

"The Health & Safety of our staff and customers is a vital part of the company's quality process. We operate a comprehensive Health & Safety Policy (see Appendix 1) covering all aspects of our products (services) and operations and it is reviewed biannually." Warwick's version for a firm with fewer than five staff: "Although we are not required legally to have a Health & Safety Policy, we take this matter very seriously and have adopted a Health & Safety Policy in the interests of our staff and clients".

Weak: quality assurance (Warwick District Council)

"We operate our own quality system. We have determined that formal accreditation is inappropriate to our company's needs. Complaints are the responsibility of the Managing Director."

Strong: quality assurance (Warwick District Council)

"We regard quality as a vitally important part of our business activity and we operate a comprehensive strict internal quality assurance process covering all aspects of our business activity (details can be found in Appendix 2). We are committed to a process of continuous improvement and we are in the process of applying for ISO 9001 (we expect to be assessed in May of this year)".

The weak answers give the evaluator nothing to score. The strong ones say what the policy covers and how often it is reviewed, and turn a gap into a dated commitment, converting "areas of weaknesses into areas of strength" (GOV.UK)27.

What a buyer says about an AI-written answer

The Scottish Government published an AI-generated answer and its critique: "no substantive detail as to how the catering company in the example would deliver the service". "It is always essential that there is human intervention and contribution by bidders prior to submitting their bids"6. Liverpool's 2026 tender asked bidders to declare their "Use of Artificial Intelligence (AI) in your submission"13.

Weak (hypothetical): mobilisation

Question: "Describe how you will mobilise the service within eight weeks of award, including the transfer of staff and data and how you will report progress to the Council." Answer: "We have extensive experience of mobilising contracts of this type and will work closely with the Council to ensure a smooth transition. Our dedicated and highly experienced team will ensure all requirements are met."

Strong (hypothetical): mobilisation

"We will complete mobilisation in seven weeks, one week inside the eight required at Specification 4.2, against a 23-task plan owned by our Operations Manager, who led our 2025 mobilisation for [named client] (six weeks, 14 staff transferred under TUPE, no missed service in month one; reference attached). Week 1: TUPE data request and staff briefings. Weeks 2 to 4: recruit the two operatives priced in Schedule 3. Week 5: migrate the Council's 1,840 site records, checked against a 5% sample with your contract manager. Weeks 6 to 7: parallel running and sign-off. Progress: a red-amber-green report every Friday against KPIs 1 to 4. Risk: late TUPE information from the incumbent; we request it in week 1 and hold week 8 as contingency, so the Council's start date is protected."

The strong version answers in its first sentence, cites the buyer's clause and KPIs, names a role, evidences past delivery and names a risk. The weak one describes the company.

After the result

Under the Act every assessed bidder receives, before the award notice, the winning tender's score and explanation per criterion, its own, and why it did not win9. Standstill is at least eight working days from the award notice, and a challenge "issued and notified during the standstill period" suspends signature, so read the summary the day it arrives10. Framework call-offs need no summary and have no mandatory standstill810.

Compare Where Then
Your score against the winner's, criterion by criterion The assessment summary9 Rank the gaps by weight × difference. The top two are the next bid's rewrite list
The reason given for each of your scores The explanations8 Match each reason to a line in your answer: missing requirement, thin evidence and unclear writing need different fixes
Why a higher score was not given Paragraph 268 If it is missing, ask in writing for the requirements not demonstrated
The winner's price and social value scores The summary Recalibrate your price model and social value offer for this buyer
Your own process The bid file Hours per question against marks won

Keep a loss log, one row per bid, and hold a lessons-learned session win or lose5. Frameworks reopen (How to get on a framework), so a loss is a gap list, not a verdict.

  • The Chest / ProContract. The free portal used by "over 30" North West councils32; Liverpool City Council, GMCA and TfGM use the same ProContract portal. Ask clarifications through its messaging area, "otherwise you are not guaranteed a response"15.
  • Lancashire County Council uses its own Fusion Supplier Portal and Find a Tender33; its free Consortium Exchange helps firms find joint-bid partners34.
  • Read before your next council bid: Liverpool's Cabinet appendix of 13 October 202613 and Cheshire East's supplier tips of March 202515.
  • Meet the buyer. Lancashire County Council's free children's services event: County Hall, Preston, 19 October 2026, 10:00 to 13:00, or a webinar35. STAR Procurement's joint event for its six councils ran on 29 January 2026; no 2027 date was published at 18 October 202636. See Relationships first.
  • Live tenders matched to North West sectors are on the explore page.

Pitfalls

Grahame Steed's ten common mistakes (Tracker Intelligence, a tender-alert service), condensed, plus three from the buyer rules above25:

Pitfall What it costs Fix
Misreading requirements, missing a pass/fail Rejection before scoring Compliance matrix; the clarification period
Incomplete submission: pricing schedule missing, form of tender unsigned, no insurance certificate Non-compliant Matrix signed off by someone outside the bid
Not answering the question A 2 or a 3 at best The question's headings and keywords as yours
Word, page, font and file-naming rules ignored Excess "likely disregarded"25; the whole tender may be7 Count every answer
Unsupported claims "minor weaknesses", "some good evidence": a 3 A number or a name beside every claim
Generic, copy-and-paste bids Reads like everyone else's The buyer's terminology and documents, cited
Poor pricing, too high or unsustainably low Price points lost, or an abnormally-low notice Model the formula; write down the logic
Vague social value Scored comparatively against the best offer at Liverpool13 Social value that scores
Portal problems Nothing submitted Register early; test uploads and file sizes
Late "cannot be accepted"15 Internal deadline 24 hours early; receipt kept
Describing the company, not the method Nothing scorable Skeleton part 3: who, what, when
Relying on what the buyer already knows "Prior knowledge ... cannot be taken into consideration"15 Write as a stranger
Altered templates, unrequested attachments, marketing "may also invalidate your response"15 Return documents as issued

Checklist: before you press submit

Questions

How are UK public sector tenders scored?

Against published weightings for quality, price and social value. Evaluators mark each quality answer on a 0 to 5 ladder independently, then moderate; price is usually scored against the lowest bid11613.

What is the difference between a 3 and a 5 in a tender evaluation?

On Liverpool City Council's 2026 ladder a 3 "contains minor weaknesses or lacks clarity"; a 4 has "no weaknesses"; a 5 adds "some areas of the service above the level of requirements"13.

How is price scored in a tender?

Most often lowest bid ÷ your bid × the price weight: with a weight of 40, £50,000 against a lowest £40,000 scores 3216. The tender documents must state the method7.

What is a method statement and how should I structure it?

Your account of how you will deliver a requirement: the direct answer, then method with named roles and timings, evidence, KPIs, risks and added value, in the question's order2422.

Can evaluators take into account what they already know about my company?

No. "Prior knowledge/experience/assumptions etc. cannot be taken into consideration" (Cheshire East)15. Incumbents must write their track record into the answer.

What feedback do I get if I lose a public tender?

Under the Procurement Act 2023, an assessment summary: your scores and reasons and the winner's, criterion by criterion9.

How long does it take to write a tender?

GOV.UK says "it can take up to 10 days to construct a good bid and sometimes more for larger and complex contracts"26. The minimum tendering period is 25 days for electronic tenders and can be 1011, so write case studies and CVs before the notice appears.

Sources

  1. Scottish Government, Procurement Journey, Route 3: technical evaluation (guidance to buyers). https://procurementjourney.scot/route-3/evaluation/technical-evaluation ↩↩↩↩↩↩

  2. Scottish Government, Supplier Journey: evaluation, with example 0 to 4 and 0/25/50/75/100 scales. https://www.supplierjourney.scot/supplier-journey/bid-process/evaluation ↩

  3. Scottish Government, Supplier Journey: tender clarification. https://www.supplierjourney.scot/supplier-journey/receipt-bids/tender-clarification ↩

  4. Scottish Government, Supplier Journey: bidding hints and tips. https://www.supplierjourney.scot/additional-resources/bidding-hints-tips ↩↩↩

  5. Scottish Government, Supplier Journey: was your bid unsuccessful? https://www.supplierjourney.scot/supplier-journey/decision-and-award/was-your-bid-unsuccessful ↩

  6. Scottish Government, Supplier Journey: an example of AI being used to write bid content. https://www.supplierjourney.scot/additional-resources/example-ai-being-used-write-bid-content ↩

  7. GOV.UK, Procurement Act 2023 guidance: assessing competitive tenders (methodology, relative scoring, abnormally low tenders, grounds to disregard). https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-procure-phase/assessing-competitive-tenders-html ↩↩↩↩↩↩

  8. GOV.UK, Procurement Act 2023 guidance: assessment summaries, paragraphs 10, 22 to 27 and 41. https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-procure-phase/guidance-assessment-summaries-html ↩↩↩↩↩

  9. The Procurement Regulations 2024, SI 2024/692, regulation 31: contents of assessment summaries. https://www.legislation.gov.uk/uksi/2024/692/regulation/31 ↩↩↩

  10. GOV.UK, Procurement Act 2023 guidance: contract award notices and standstill. https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-procure-phase/guidance-contract-award-notices-and-standstill-html ↩↩↩

  11. GOV.UK, Procurement Act 2023 guidance: time periods (minimum tendering periods, paragraph 20). https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-procure-phase/time-periods-html ↩

  12. GOV.UK, Procurement Act 2023 guidance: conditions of participation (section 22: proportionality, no insurance before award). https://www.gov.uk/government/publications/procurement-act-2023-guidance-documents-procure-phase/guidance-conditions-of-participation-html ↩

  13. Liverpool City Council, Cabinet, 13 October 2026, "Award of Contract: Parking Enforcement and Permit Services Transformation Programme", Appendix 1, Evaluation Outcome and Award Recommendation (not exempt): weightings (Table 1), technical categories (Table 2), descriptors (Table 3), scores (Table 5), moderation, thresholds, clarifications, the AI declaration and the evaluator comment. https://councillors.liverpool.gov.uk/documents/s329288/Appendix%201%20Evaluation%20Outcome%20and%20Award%20Recommendation%20-%20not%20exempt.pdf ↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩↩

  14. Liverpool City Council, Cabinet, 13 October 2026, report PR1194 (DN817006): route, estimated value and closing date. https://councillors.liverpool.gov.uk/documents/s329286/Penalty%20Charge%20Notice%20and%20Permit%20Management%20System.pdf ↩

  15. Cheshire East Council, "Supplier guidance on submitting quotation and tendering responses: top tips", March 2025 (PDF). https://www.cheshireeast.gov.uk/pdf/business/doing-business/supplier-guidance-on-submitting-quotations-and-tender-responses.pdf ↩↩↩↩↩↩↩↩↩↩↩↩↩↩

  16. Brent Council, Invitation to Tender evaluation criteria and scoring matrix (Appendix 2), 2017, under the Public Contracts Regulations 2015. https://democracy.brent.gov.uk/documents/s63020/Appendix%202%20-%20Invitation%20to%20Tender%20ITT%20evaluation%20criteria%20and%20scoring%20matrix.pdf ↩↩↩↩↩↩↩↩↩

  17. Thornton & Lowe (bid consultancy), Charles Grosstephan, "What to do first when an ITT lands", 23 July 2026. https://thorntonandlowe.com/itt-what-to-do-first/ ↩↩↩

  18. Thornton & Lowe, "The right pricing strategy", 16 April 2024. https://thorntonandlowe.com/the-right-pricing-strategy/ ↩↩

  19. Thornton & Lowe, Charles Grosstephan, "Abnormally low tenders explained", 13 January 2026. https://thorntonandlowe.com/abnormally-low-tenders/ ↩

  20. Executive Compass (bid consultancy), Ciaran Brass, "The importance of tender compliance in your bid process", 2 July 2026. https://www.executivecompass.co.uk/blog/top-tips/the-importance-of-tender-compliance-in-your-bid-process/ ↩

  21. Executive Compass, Ciaran Brass, "Lessons from 16 years of winning tenders", 25 February 2026. https://www.executivecompass.co.uk/blog/bid-management/lessons-from-16-years-of-winning-tenders/ ↩↩↩

  22. Executive Compass, "The art of persuasion in bid writing: don't just explain, persuade", 18 September 2026. https://www.executivecompass.co.uk/blog/bid-management/the-art-of-persuasion-in-bid-writing-dont-just-explain-persuade/ ↩↩↩↩↩↩↩

  23. Executive Compass, Ciaran Brass, "Seven quick wins to improve your tender quality scores", 24 June 2026. https://www.executivecompass.co.uk/blog/top-tips/seven-quick-wins-improve-tender-scores/ ↩↩↩

  24. Stotles, "How to write a tender proposal that wins in 2026". The 60/40 and 70/30 splits are the platform's estimate; no public dataset confirms them. https://www.stotles.com/resource/blog/how-to-write-a-tender-proposal ↩↩↩↩↩↩

  25. Grahame Steed, "Common mistakes suppliers make in tender submissions", Tracker Intelligence. https://www.trackerintelligence.com/resources/procurement-news/common-mistakes-suppliers-make-in-tender-submissions/ ↩↩↩↩↩↩↩

  26. GOV.UK, "VCSEs: a guide to working with government", updated 21 July 2026. https://www.gov.uk/guidance/vcses-a-guide-to-working-with-government ↩↩↩↩

  27. GOV.UK, "How to bid for government contracts as an SME effectively", Cabinet Office and Department for Education, last updated 23 March 2023. https://www.gov.uk/guidance/how-to-bid-for-government-contracts-as-an-sme-effectively ↩↩↩

  28. Government Commercial Agency, "Write effective bids". https://www.gca.gov.uk/how-to-supply/write-effective-bids ↩

  29. Warwick District Council, "How to do business with Warwick District Council", page 4: example weak and good answers. https://www.warwickdc.gov.uk/info/20010/business_procurement/1518/how_to_do_business_with_warwick_district_council/4 ↩

  30. Bracknell Forest Council, "Schedule 1 Method Statement Detailed Proposal Response Document", insurance and claims handling, 2019 (PDF). https://www.bracknell-forest.gov.uk/sites/default/files/2021-11/2019%20Insurance%20Method%20Statement.pdf ↩↩

  31. Westmorland and Furness Council, "Procurement and tendering". https://www.westmorlandandfurness.gov.uk/business-and-licensing/procurement-tenders-and-social-value-opportunities/procurement-and-tendering ↩

  32. Cheshire East Council, "e-tendering": The Chest "is used by over 30 North West local authorities". https://www.cheshireeast.gov.uk/business/procurement/doing_business/e-tendering.aspx ↩

  33. Lancashire County Council, "How to do business with the county council". https://www.lancashire.gov.uk/business/tenders-and-procurement/how-to-do-business-with-the-county-council/ ↩

  34. Lancashire County Council, "Consortium Exchange". https://www.lancashire.gov.uk/business/tenders-and-procurement/consortium-exchange/ ↩

  35. Boost Business Lancashire, "In Person LCC Meet the Buyer Event for Children's Services", 19 October 2026, County Hall, Preston. https://www.boostbusinesslancashire.co.uk/events/in-person-lcc-meet-the-buyer-event-for-childrens-services ↩

  36. STAR Procurement, "Meet the Buyer 2026", 29 January 2026. https://www.star-procurement.gov.uk/Events/Meet-the-Buyer-2026/Star-Procurement-Events.aspx ↩

Written for businesses, founders and researchers in the North West of England and checked against the sources listed above on 18 October 2026. Funders change their rules, so always read the current call before you apply. Spotted something out of date? Tell us.

Put it to work